What happens to my budget and schedule when something changes?

A change should be evaluated for its cost, schedule, and effect on other work before you approve it. Clear documentation helps everyone understand what is changing and how it will be handled under the contract.

Take a closer look

Open any section for the questions, checks and decisions behind the short answer.

Ask the team to identify the original requirement, the proposed revision, and the reason for it. A request to move a wall needs more detail than a marked-up sketch: which drawing changes, which rooms are affected, and what work is already installed or ordered?

Keep the reason separate from the question of who is responsible for the cost. An owner preference, an existing condition uncovered during work, and a design clarification can require different treatment under the agreement. Document the facts and have the appropriate project professionals review responsibility rather than deciding it from a brief jobsite conversation.

Ask for a breakdown that makes the proposed adjustment understandable. Where relevant, it should show added work, deleted work, credits, and the contract basis for applicable markups. Check whether the proposal includes related trades and design revisions or leaves them for a later price.

For example, with an equipment substitution, the purchase-price difference may be only one part of the decision. Ask whether the new unit changes electrical service, plumbing connections, ventilation, clearances, supports, or delivery access. Those are questions for the contractor and design team to investigate, not costs to assume automatically.

Ask what remains uncertain and when the pricing expires. If the change adjusts an allowance or uses contingency, ask the team to show the allowance reconciliation, any contingency use, and the resulting contract adjustment under your agreement.

A useful schedule explanation connects the change to actual work. Ask when revised information is needed, whether material availability has been checked, and what cannot proceed until the decision is made. Identify any work that must be removed, repeated, or resequenced.

AIA guidance calls for evaluating whether a change affects the critical path, the connected activities that govern completion. A longer delivery time does not, by itself, establish an identical extension to the entire project. Ask the contractor to explain the relationship and identify possible adjustments to other work.

If the proposal says there is no schedule effect, have that recorded. If the effect is still being evaluated, make that uncertainty visible before making staffing, move-in, or opening announcements.

Confirm who can request pricing, review it, and authorize a change. In the AIA change-order model, the owner, contractor, and architect document agreement on the work and any adjustment to price and time. Your project may use a different delivery structure or modified agreements, so follow its actual requirements.

The owner decides business priorities and spending authority. The contractor evaluates construction pricing and sequencing. The architect or engineer reviews design implications within the services they are engaged to provide. Keep these roles visible when an answer needs input from more than one person.

Some contracts provide a formal directive process when changed work must proceed before price or time is settled. Ask how that process handles authorization, records, valuation, and later agreement. An unresolved amount should remain clearly identified.

After authorization, check that the change appears in the change log, current drawings, contract value, and schedule as applicable. Tell affected owner vendors about revised requirements through the agreed coordination process.

Keep approved changes, pending proposals, and remaining contingency visible separately. A budget report that shows only signed changes can hide potential exposure from unresolved items. Request a current view of what is committed, what is being evaluated, and what funds remain available.

If a change is declined or deferred, record that outcome too. Include the version of the proposal and any follow-up required so the team does not continue working from an earlier conversation.

The lounge and coffee area in Edge Crew’s Halsell Street office.

A six-question change review

Use these prompts before making an owner decision. Keep the supporting proposal and revised drawings with the record.

01

What exact work changes, and which dated documents describe it?

02

What is the net price, including credits, exclusions, and unresolved amounts?

03

Which activities or milestones are affected, and why?

04

What decision date, pricing validity, or material availability matters?

05

Who must review and authorize this under our agreements?

06

What are the updated project forecast and remaining contingency?

This guide offers general planning questions. Your contract, design documents, property conditions and applicable approvals determine the requirements for your project.